Concerns Raised Over Oversight in $17 Million Muan International Language and Culture Center Project

by Kim ok Hyun Posted : September 8, 2026, 08:52Updated : September 8, 2026, 08:52

The Muan Office of Education has come under scrutiny for proceeding with a 17 billion won ($13 million) construction project for the Muan International Language and Culture Center without the required environmental notifications, raising concerns about oversight and management.


Notably, construction continued on Sundays, a fact the contracting agency, the Office of Education, claimed it was unaware of, highlighting significant gaps in the project’s oversight system.


According to the Muan Office of Education, the project involves remodeling the main building and dormitory, as well as reconstructing parking lots and playgrounds at the Glocal Education Center in Gojol-ri, Muan-eup, with a total budget of approximately 17.7 billion won. The construction began on March 4 and is scheduled to be completed by August 30.


However, an investigation revealed that the relevant environmental department had not received any notifications regarding dust emissions or specific construction activities related to this project.


A representative from the Muan County Environmental Department stated, "As of now, there have been no reports submitted regarding dust emissions or specific construction activities related to this project."


Despite the lack of notifications, construction has continued, including work on Sundays. Furthermore, the construction supervisor from the Muan Office of Education claimed to be visiting the site frequently but failed to recognize that essential environmental notifications had not been completed prior to the start of construction.


The construction supervisor is responsible for ensuring the quality and safety of the work, as well as compliance with contractual obligations and relevant laws. The fact that the failure to report was not identified until after construction began raises questions about whether the review of construction documents and site management were conducted adequately.


The head of the facilities team at the Muan Office of Education stated, "We determined that there are no residential areas within 300 meters, so we considered it exempt. If it needs to be corrected in consultation with the county, we will take immediate action."


Reporting dust emissions and specific construction activities is a legal requirement that must be fulfilled before starting construction for projects of a certain scale. The relevant administrative agency will investigate whether the project falls under the reporting requirements and whether any legal violations occurred before deciding on administrative actions.


In light of this situation, local construction industry representatives have pointed out that the failure to confirm basic legal notifications in a public project worth 17 billion won is not solely the contractor's issue but also raises concerns about whether the oversight system of the contracting agency is functioning properly.