Government to Focus on 16 Key Road Projects in New Cities to Reduce Permit Delays

The government will focus on addressing permit delays for 16 key road projects in new cities, including Hanam Gyosan and Incheon Gyeyang. The plan aims to expedite administrative procedures and reduce traffic inconveniences for residents.


On November 10, the Ministry of Land, Infrastructure and Transport's Metropolitan Transportation Commission announced that it will hold a joint inspection meeting for the 'New City Traffic Measures Rapid Implementation Task Force' on November 11. Participating agencies include Incheon City, Hanam City, Siheung City, Ansan City, and the Korea Land and Housing Corporation (LH).


The inspection will focus on 'fast-track permit' road projects among the metropolitan transportation improvement measures, which can have their permit periods shortened through inter-agency consultations.


Key projects include the connection road from the Gaksan Tunnel in Hanam Gyosan to National Route 43, the connection road to National Route 39 in Incheon Gyeyang, and the underground urban expressway between Gwacheon and Umyeonsan, along with the expansion and integration of the Sangae Valley underpass.


In the Ansan Jangsan District, three underpasses at the post office in Suam-dong, the newly established intersection, and the Jeil CC intersection are also on the inspection list.


In the Uiwang-Gunpo-Ansan District, the inspection will cover the expansion of Haian Road in Ansan and the new connection road from the project site to Suin Road, as well as the new connection road to Yongdam IC.


In the Siheung Janghyeon and Mokgam Districts, six projects will be reviewed, including the road construction between Jukyu, Janghyeon, and Mokgam, the Janghyeon-Sanhyeon intersection, the expansion of the road between Ansan and Gahak, and the Moolwang-Gumi intersection.


During the meeting, the Metropolitan Transportation Commission will confirm the design and permit progress for each road project, as well as future schedules, and address any difficulties encountered during the project process. The commission plans to coordinate roles among participating agencies to prevent delays caused by inter-agency consultation lags or overlapping administrative procedures and to support swift decision-making.


Some projects have already begun construction. According to the Metropolitan Transportation Commission, two projects, including the underground urban expressway between Gwacheon and Umyeonsan in the Gwacheon public housing district, received project plan approval in October and have commenced work. These projects began construction approximately 10 months after the project plan approval application was submitted in December of last year, with a target completion date set for October 2031.


In April, the Metropolitan Transportation Commission selected 36 projects among the metropolitan transportation improvement measures for focused management. These projects are categorized into 'conflict resolution type,' which adjusts inter-agency conflicts based on project characteristics; 'fast-track permit type,' which supports the shortening of administrative procedures; and 'direct permit type,' where the Ministry of Land, Infrastructure and Transport directly approves project plans.


The commission will also review recurring permit delay factors and structural issues during this inspection. If necessary, it plans to identify institutional improvement tasks to apply to other new city transportation measures.


Moon Seok-jun, acting director of the Metropolitan Transportation Policy Bureau, urged, "Agencies must thoroughly manage project schedules and closely share matters requiring inter-agency consultation with the Metropolitan Transportation Commission to ensure that subsequent procedures are not delayed."





* This article has been translated by AI.