Concerns Grow Over Transportation Infrastructure for New Towns Ahead of Move-In Dates

The government's inadequate transportation plans for the third-phase new towns are under scrutiny. With move-ins approaching in about a month for the Gyeyang district in Incheon, as well as in Wangsu, Namyangju, and Gyosan, delays in transportation measures are expected to cause inconvenience for residents.


According to the Ministry of Land, Infrastructure and Transport and the Korea Land and Housing Corporation (LH), transportation plans for Blocks A2 and A3 in the Gyeyang district, set to welcome residents next month, have yet to be finalized. Alternatives for rail services have not been determined, and major roads are scheduled for completion only after residents move in. LH plans to deploy nine shuttle buses, with capacities of 45 and 28 passengers, across three routes to begin operations simultaneously with the move-ins. However, specific routes and schedules remain undecided due to ongoing consultations with local governments.


The government initially aimed to finalize the district plan for Gyeyang in June 2021, targeting first move-ins in 2025 and completion of transportation measures in 2026. However, the move-in schedule has been delayed by a year, pushing back transportation plans as well. The expansion of National Route 39 (Beolmal-ro) has been postponed from this year to 2031. Additionally, the key regional transportation system, S-BRT (from Gimpo Airport Station to Bakchon Station), has not yet been confirmed.


Concerns are growing that inadequate transportation measures could extend beyond Gyeyang to the entire third-phase new town initiative. By 2029, an additional 9,715 units in Geomdan, 13,623 units in Gimpo, and 2,399 units in Gyeyang are expected to be occupied. With over 25,000 units slated for subsequent occupancy, a significant portion of commuting demand to Seoul is anticipated to concentrate on existing rail lines, such as Gyeyang Station and Gimpo Airport Station.


Other third-phase new towns face similar challenges. According to data submitted by LH to the National Assembly in September, 77 out of 89 regional transportation improvement projects (86.5%) have experienced delays. Fifty-eight projects are not expected to be completed until after 2030, with some lacking a definitive completion timeline.


Rail and key road projects have also faced delays. The Gangdong-Hanam-Namyangju Line in Wangsu and the Songpa-Hanam Line in Gyosan are now targeted for completion in 2032, while the Goyang-Eunpyeong Line in Changneung is set for 2031. These deadlines have been pushed back by one to two years from their original targets of 2031, 2030, and 2029, respectively. The expansion of the Han River Bridge and Olympic Boulevard in Wangsu has been delayed from 2028 to 2032, and the connection road from Jungang-ro to the Second Freeway in Changneung has been postponed from 2025 to 2031.


Seojin Hyung, a professor at Kwangwoon University’s Department of Real Estate Law, expressed concern, stating, “The installation of regional transportation and infrastructure within the third-phase new towns is being delayed. The government has promoted a 'transportation first, move-in later' policy, but the establishment of transportation networks in Gyeyang, which is set to welcome residents at the end of this year, is already falling behind. This could weaken living conditions and market absorption capacity even after move-ins begin.”