Vietnam's Long Thanh International Airport Set to Open in December

Vietnam's largest airport, Long Thanh International Airport, is accelerating preparations to welcome its first passengers ahead of its commercial operations set to begin in December. Fifty airport staff members took on the role of passengers to test the entire boarding process, from check-in to immigration control, as part of the final preparations for the airport's opening.


According to local media outlet Thanh Nien on November 15, Long Thanh International Airport, located near Ho Chi Minh City, recently conducted a simulation operation to check domestic and international passenger processing as part of the ORAT (Operational Readiness and Airport Transfer) program.


The simulation involved 50 participants, including airport officials and staff from related agencies. They verified passenger movement routes and airport operational procedures across three scenarios: domestic departures, international departures, and international arrivals. Participants went through the same procedures as actual travelers, from receiving boarding passes at airline check-in counters to security checks, immigration control, quarantine, and customs.


The airport management also examined whether passenger and baggage information was communicated effectively at each stage. The accuracy of access control devices at boarding gates and passenger information systems was also a key focus of the checks.


Accessibility Measures for Wheelchair Users Tested Ahead of December 24 Opening


Following the general passenger simulation, a separate test was conducted for passengers with mobility challenges. The airport assessed the support procedures necessary for passengers with disabilities, including those using wheelchairs, during domestic and international flights and transfers.


Specifically, the process was evaluated from the moment wheelchair users entered the terminal through check-in, security screening, immigration control, and boarding. Procedures to assist passengers in retrieving their luggage and safely moving through the arrivals area after their flights were also tested.


Additionally, checks were conducted on facilities for passengers with disabilities, including elevators, restrooms, signage, priority check-in counters, and dedicated pathways. This simulation is part of the ORAT program, which aims to verify that airport facilities, personnel, and IT systems function properly in a real operational environment.


ORAT is a comprehensive testing procedure for airport facilities, equipment, personnel, and operational systems before opening. It typically consists of five stages: planning and preparation, trial operations and evaluation, operational handover, and post-opening support.


Currently, Long Thanh International Airport is simultaneously conducting construction and equipment installation while progressing through various stages of ORAT. An airport official stated, "Given the complexity of transitioning to large-scale aviation facilities, we aim to confirm inter-agency cooperation and resolve technical and operational issues before the opening through these preliminary tests." The airport plans to expand the scale of future simulations to further validate its response capabilities in various scenarios.


Meanwhile, Long Thanh International Airport is scheduled to commence commercial operations at midnight on December 24. According to the initial operational plan prepared by the Airports Corporation of Vietnam (ACV), the airport will handle a maximum of approximately 366 flights per day, including 322 domestic flights and 44 international flights.


As the official opening approaches, checks on passenger processing procedures and support systems for individuals with disabilities are underway, with a focus on addressing any technical issues and inter-agency cooperation challenges identified during the trial operations.