Czech Republic Accelerates Selection of New Contractor for Dukovany Nuclear Power Plant

The Czech Republic is accelerating the selection of a new contractor for the Dukovany Nuclear Power Plant project following the breakdown of negotiations for the construction contract. The government aims to strengthen communication with the Czech contracting authority and monitor the implementation of weekly detailed plans by Korea Hydro & Nuclear Power to minimize the potential for construction delays.


The Ministry of Trade, Industry and Energy announced that Vice Minister Park Dong-il chaired the 'Second Meeting on Korea Hydro & Nuclear Power's Implementation Plans' at the Korea Chamber of Commerce and Industry in Seoul on the 18th to review the project's progress. This meeting is part of the emergency management system led by the ministry's ministers and vice ministers that began this month.


Previously, Korea Hydro & Nuclear Power ended negotiations with the Daewoo Engineering & Construction and Doosan Enerbility consortium regarding the construction contract for the Dukovany Nuclear Power Plant on October 29. The breakdown was due to an inability to narrow differences over construction costs and contract terms, and Korea Hydro & Nuclear Power has since initiated follow-up procedures for selecting a new contractor.


On this day, Korea Hydro & Nuclear Power reported detailed plans to ensure the continuity of existing construction-related tasks, including design, permitting, site information verification, and selection of accommodation sites. The selection of a new contractor is also being managed on a weekly basis until the end of this year, with the company stating that it has successfully implemented plans up to the third week of November.


During a review meeting on the 12th, Korea Hydro & Nuclear Power set a goal to select a new contractor by July 2027. Until the contractor is selected, the company plans to deploy additional personnel to carry out some tasks directly and to proceed with urgent auxiliary facility designs through separate contracts.


The key project timeline managed by the government includes applying for construction permits in April 2027 and commencing construction in November 2029. Ensuring that major permits and design schedules are not delayed during the new contractor selection process is identified as a core task.


Communication with the Czech side is also being strengthened. Korea Hydro & Nuclear Power participated in a video conference with the Czech Ministry of Industry and Trade at the director level on the 5th and discussed key issues with the Czech contracting authority, the Dukovany II Nuclear Power Company (EDU II), during their visit to Korea from November 9 to 12.


Vice Minister Park Dong-il emphasized, "By thoroughly implementing a systematic plan that supports the achievement of key milestones, we will ensure the normal progress of the project. We must push forward with greater speed while adhering to quality and price commitments to prepare for unexpected schedule delays."


He also urged the active use of the 4th Korea-Czech ministerial implementation review meeting and monthly ministerial meetings, as well as weekly director-level meetings scheduled for December 10 in Korea, to closely discuss current issues with the Czech side.





* This article has been translated by AI.