Doosan Enerbility Secures Global Insurance Conditions for Yawol Offshore Wind Turbines

Doosan Enerbility's 8MW offshore wind turbines will be subject to global insurance conditions applicable to offshore wind projects.


On November 20, Doosan Enerbility announced that the Yawol Offshore Wind Farm in Yeonggwang, South Jeolla Province, has secured insurance that includes the 'LEG 2' conditions. LEG 2 is an international insurance clause that defines the compensation scope for damages arising from design, material, and construction defects, utilized in construction and installation projects such as offshore wind farms.


The Yawol Offshore Wind Farm is a 104MW project being developed off the coast of Nakwol-myeon in Yeonggwang-gun, South Jeolla Province, where 13 units of the 8MW offshore wind turbine 'DS205-8MW' will be installed.


Doosan Enerbility will be responsible for the design, procurement, and construction (EPC) of the wind turbines. After completion, the company plans to manage the operation and maintenance of the wind farm through a long-term service agreement (LTSA).


Prior to this insurance acquisition, global insurance broker Willis Towers Watson and reinsurer Swiss Re reviewed the technical risks associated with Doosan Enerbility's 8MW and 10MW offshore wind turbines.


The two companies examined the design and certification systems, major component test results, prototype operation data, and manufacturing and quality control systems. As a result, they concluded that it is possible to apply the LEG 2 conditions to the insurance underwriting for the DS205 turbine, based on individual project reviews.


The DS205 developed by Doosan Enerbility is a large-capacity offshore wind turbine designed for low wind speed environments in South Korea. The 8MW model received international type certification in 2022, while the 10MW model obtained certification in 2025.


To date, Doosan Enerbility has secured orders for a total of 111 wind turbines, amounting to approximately 452MW. The company is expanding its business not only in wind turbine supply but also in offshore wind farm EPC and maintenance.


Song Yong-jin, CEO of Doosan Enerbility, stated, "It is significant that our offshore wind turbines have been applied with globally recognized insurance conditions in actual commercial projects. Based on our proven technology and accumulated EPC and service capabilities, we will continue to expand reliable offshore wind solutions for our customers."


Meanwhile, Doosan Enerbility announced on the 6th that a consortium in which it participates, led by Korea Hydro & Nuclear Power, has been selected as the preferred bidder for the first phase of the Southwest Offshore Wind Expansion Project.





* This article has been translated by AI.