37% of Major Redevelopment Projects in Seoul Lack Transparency

Among redevelopment projects in Seoul that have entered the post-approval phase, 37% have fallen short of the city's transparency evaluation, according to a report by Aju Economy. More than half of the projects in the sales phase also received similar results. Experts are calling for enhanced management of information disclosure to ensure that key data, such as construction costs and member contributions, can be accessed in a timely manner.


On November 2, Aju Economy analyzed the list of redevelopment projects under the Seoul city initiative 'Comprehensive Information on Maintenance Projects.' A total of 320 housing maintenance-type redevelopment projects were identified, with 64 registered as operational at various stages, including project approval, management disposition approval, demolition, construction commencement, and sales.


Of the 64 projects, transparency scores were calculated for 59, with 22 projects (37.3%) scoring below 100%. This indicates that some projects did not receive adequate evaluations due to delays in public disclosure or lack of available data.


In the sales phase, 4 out of 7 projects (57.1%) scored below 100%. In the demolition phase, 3 out of 6 projects (50%) fell short. In the project approval phase, 7 out of 17 projects (41.2%) did not meet the standard, while in the management disposition approval phase, 6 out of 18 projects (33.3%) were below 100%. In the construction commencement phase, 2 out of 11 projects (18.2%) also failed to achieve full transparency.


There were significant differences in scores among projects. In the project approval phase, North Ahyeon District 3 received a transparency score of 0%, while Shinjeong 1 Redevelopment Promotion District 3 scored 7.69%. In the sales phase, Noryangjin District 8 scored 30.77%, Jangwi District 10 scored 40%, and Haengdang District 7 scored 60%.


In the management disposition approval phase, Bongcheon District 4-1-3 and Bongcheon District 14 both scored 80%. In the demolition phase, Jegi District 4 scored 66.67%, Sinlim District 2 scored 83.33%, and Hannam District 3 scored 93.33%. In the construction commencement phase, Noryangjin District 6 scored 83.33%, and Heukseok District 9 scored 95.83%, both below 100%.


Transparency scores are automatically calculated by the Seoul city system, which evaluates new public data and the handling of requests for missing data twice a month. This does not reflect the cumulative disclosure rate of all project data and is based on the city's own criteria, separate from legal disclosure deadlines.


According to Article 124 of the Urban and Residential Environment Maintenance Act, key documents such as articles of incorporation, contracts for service providers, minutes from general meetings, business implementation plans, management disposition plans, audit reports, and monthly financial statements must be disclosed within 15 days after they are created or amended.


Even after project approval, decisions affecting construction cost increases, contract changes, relocation costs, contributions, and general sales continue to impact member burdens and asset values.


A maintenance project official stated, “As redevelopment projects progress, decisions regarding construction costs, contributions, and contract changes increasingly affect members' property rights. The law sets specific deadlines for information disclosure to ensure that members can make informed decisions, so stricter management of timely disclosures is necessary, especially in the later stages of projects.”