Critics Say Government Support for Semiconductor Investment Falls Short


Samsung Electronics and SK Hynix are accelerating the establishment of a large-scale semiconductor production belt centered around Yongin and the southwestern region, but critics argue that government support is minimal. Despite being a critical national project, direct and indirect financial assistance accounts for less than 1% of the total investment. Concerns are growing that the Yongin semiconductor cluster, set to begin operations next year, may face initial setbacks due to a lack of infrastructure funding.

According to industry sources and relevant government departments, of the 34 trillion won allocated for semiconductor budgets next year, 15 trillion won will be used for integrated financial support for the southwestern cluster. A total of 60 trillion won is planned to be invested over the next four years. An additional 3 trillion won has been earmarked for relocating the Gwangju military airport. Samsung and SK Hynix have pledged an investment of 800 trillion won in the southwestern region. For every 10 trillion won invested by companies, government support amounts to only 7.5 billion won.

The situation at the existing Yongin cluster is even more strained. SK Hynix plans to invest 600 trillion won in Yongin and has accelerated the completion of its fourth fab from 2045 to 2033. Samsung Electronics is also ramping up its investment in the Yongin national industrial complex, committing 360 trillion won. However, the budget for early operational infrastructure for the Yongin and Pyeongtaek fabs is limited to just 1 billion won, which is only one-fifteenth of the annual support for the southwestern region.

Industry insiders report that the costs for power lines and substations in the Yongin cluster alone amount to 24 trillion won, while the integrated water supply project costs 22 trillion won. Although the government has stipulated through the Semiconductor Special Act that 50-100% of infrastructure costs should be borne by the state and local governments, the initial budget allocation for existing sites remains minimal.

Due to the insufficient support budget, the substantial costs for infrastructure development are being shifted entirely to companies. Of the 24 trillion won needed for the Yongin cluster's power lines and substations, 70%, or 17 trillion won, will be directly borne by the companies. The southwestern region also requires new power lines to transmit energy from solar and offshore wind projects in Jeonnam and the Yeonggwang Hanbit Nuclear Power Plant to Gwangju, but no concrete funding plans have been announced.

An industry representative expressed disappointment, stating, "Given the government's repeated emphasis on the importance of semiconductor investment, we had hoped for groundbreaking support in next year's budget. However, the actual budget is so minimal that it feels like companies are being told to invest and survive on their own."

There are also complaints that even the promised infrastructure projects are not being implemented on time due to administrative and permitting delays. The expansion of the high-voltage direct current (HVDC) converter station at the Dongseoul substation, which would bring power from the East Coast to Yongin, has been stalled for over two years due to local opposition. Despite 15 rounds of discussions, no conclusion has been reached. The government and Korea Electric Power Corporation plan to hold another meeting with the residents' consultative body on the 3rd.

Another industry source noted, "Even though a government-wide task force and dedicated consultative body have been activated, on-site progress is repeatedly stalled by local government permits and resident opposition. No matter how quickly we build the fabs, if we can't operate the lines due to power and water shortages, what good will it do?"

In addition to financial support, discussions regarding exceptions to the 52-hour workweek for research and development personnel are also stalled. Due to differences in positions among relevant ministries, including the Ministry of Employment and Labor and the Ministry of Trade, Industry and Energy, no conclusion has been reached for 10 months since the Semiconductor Special Act was enacted in January.

Park Geon-soo, executive vice president of the Korea Semiconductor Industry Association, stated, "In a competition where a day’s delay can lead to a 10-year gap, the semiconductor industry is eager for the realization of special working hour provisions for core R&D personnel within this year."