The Central Labor Relations Commission has determined that if a prime contractor significantly influences the wage increase rates of subcontractor employees, it must negotiate directly with the subcontractor's labor union on wage issues.
This ruling marks the first time the commission has recognized employer status regarding wages since the implementation of the amended Labor Union Act, known as the Yellow Envelope Law. This decision is expected to impact labor relations.
According to labor sources, the commission dismissed a request for a corrective review filed by Gyeonggi Expressway against the Public Industry Hope Union regarding a negotiation demand announced in September. The reasons for the ruling were disclosed 30 days after the decision date.
Gyeonggi Expressway completed the Suwon-Osan-Pyeongtaek Expressway in October 2009 through a private investment project and has been granted operational rights by the government for 30 years.
Workers from the subcontractor, Ido, which manages the integrated operation of the Suwon-Osan-Pyeongtaek Expressway, demanded negotiations in June, asserting that Gyeonggi Expressway is the employer responsible for determining overall working conditions, including industrial safety, working hours, and wages.
However, Gyeonggi Expressway did not disclose the negotiation demand, prompting the union to file a correction request with the Gyeonggi Regional Labor Relations Commission. The commission accepted the union's claims, and the Central Labor Relations Commission respected this judgment.
The commission closely examined the five-year consignment contract between Gyeonggi Expressway and the subcontractor. Previously, Gyeonggi Expressway required the subcontractor to detail labor costs and allowances in the bidding phase, including a proposed annual wage increase rate applicable over the next five years. The calculations reflected an approximate 3% increase in the total basic salary compared to the previous year.
The prices proposed by the subcontractor during the bidding phase were determined within the range set by the prime contractor, and the subcontractor had to accept requests for supplementary business plans from Gyeonggi Expressway, which influenced the commission's judgment.
In its ruling, the commission stated, "The employer did not merely set the total consignment fee to be paid to the subcontractor but also determined the scale of personnel and the specific labor costs for each job category. This effectively controls the specific wages of subcontractor employees and how they will be increased."