Mokpo City Council Chair Criticizes Budget Planning and Audit Issues

The Mokpo City Council has raised concerns over the city's budget allocation for a public office construction project, citing a lack of sufficient funding plans and inaccuracies in submitted documents during the administrative audit process.

Park Soo-kyung, chair of the Planning and Welfare Committee, focused on the inadequate budget planning and the administration's failure to provide reliable audit materials during the second regular session of the 409th council meeting held on November 13.

Park criticized the appropriateness of the budget allocation and the effectiveness of the project plan for the Sangdong Administrative Welfare Center construction. Mokpo City submitted a budget of 40 million won for the design service of the center in its third supplementary budget proposal for the year.

However, the council withheld approval, citing the lack of clarity regarding the necessary funding for the next year's main budget. Park noted that the administration faced strong objections from local residents during this process, ultimately failing to secure the main budget for the following year, and pointed out that the project was omitted from the six major tasks outlined by the accounting department.

She criticized the decision to allocate design costs without a thorough financial review, stating it exemplified a haphazard approach to budgeting.

"The council's decision to withhold approval led to significant complaints from local residents," Park said. "Ultimately, the administration failed to secure the main budget for next year, and the omission of the project from the major tasks revealed a lack of proper budgeting practices."

She emphasized that if the council had approved the design costs at that time, it could have resulted in a waste of the 40 million won without any follow-up budget or project plan.

Park urged that when allocating public project budgets, considerations should include not only the urgency of the project but also the feasibility of securing funds, annual investment plans, and conditions for subsequent project implementation.

The administrative audit also highlighted the administration's poor document management. Park pointed out that materials requested during the previous day's audit were not submitted until the following afternoon, questioning the administration's responsiveness to legitimate requests from the council.

She specifically noted discrepancies between the contract details listed in the audit materials and those published on the Mokpo City website, calling for improved accuracy and reliability of administrative documents.

The discrepancies in the contract-related materials are fundamental audit documents necessary to verify the appropriateness of budget execution and the transparency of contract procedures, indicating a need for clarification and rectification of the inconsistencies.

Park Soo-kyung stated, "Delaying legitimate requests for document submission or providing inaccurate materials undermines the council's audit authority. The administration must approach audits responsibly and establish a thorough document management system under the responsibility of department heads."

She also called for improvements to ensure that similar issues do not recur, including diligent compliance with document submission obligations, pre-audit verification of materials, and strengthening management responsibilities by department.

This audit revealed broader issues beyond simple delays in document submission, including the connection between project plans and budget allocations, the accuracy of administrative information, and the administration's accountability to the council.

Meanwhile, as funding issues have been raised since the design cost allocation stage for the Sangdong Administrative Welfare Center construction project, the administration will need to provide specific explanations regarding the project's future implementation and funding strategies. Additionally, the reasons for the discrepancies in audit materials and published contract details will require further examination by the council.



* This article has been translated by AI.