The grid impact assessment screens in advance how a large power user would weigh on the local grid.
A draft enforcement decree of the special act on AI data centers, put out for public comment Friday, exempts new, expanded or converted facilities of 50 megawatts or less outside the greater Seoul area.
The Ministry of Science and ICT and the Ministry of Climate, Energy and Environment had weighed a 100 MW threshold, but even that would have left most gigawatt-class projects outside the exemption.
Operators also sink much of their preparation time into the non-technical part of the review.
Data centers in special zones under the act will skip the non-technical review regardless of size and face only the technical one.
Megaprojects and sites seeking bundled permit processing will be fast-tracked, a rule the climate ministry will write into its assessment manual to cut waiting times.
The capital area accounted for 71 percent of the 736 grid review applications filed from August 2024 to March 2026, according to climate ministry data, but only 10 projects there, about 1 GW of the 33.6 GW sought, won final approval.
Some 187 of 214 applications outside the region cleared the first review.
"It's merely the grid to the capital area that is saturated," said Kim Chul-hyun, a senior research fellow at the Korea Energy Economics Institute.
South Korea plans 8.4 GW of AI data center capacity by 2029 and 18.4 GW by 2035.
Copyright ⓒ Aju Press All rights reserved.
![[2026 Defense Industry Forum] Shin Beom-cheol: Beware of North Koreas Combat Experience... Innovation Requires Discarding Yesterdays Successes](https://image.ajunews.com/images/site/ajupress/v2/img/v2/ajp_noimg.png)