Korea Hydro & Nuclear Power Strengthens Local Management for Czech Nuclear Project

Korea Hydro & Nuclear Power is enhancing its local management system for the Dukovany nuclear power project in the Czech Republic to minimize operational gaps following the replacement of the construction company. The company plans to deploy personnel to Dukovany and expand cooperation with the Czech government and the ordering company to ensure that major project schedules, including the construction permit application in April next year, proceed without delays.


On November 27, Korea Hydro & Nuclear Power announced that Vice President Choi Il-kyung recently visited the Czech Republic to meet with key stakeholders, including government officials and representatives from the ordering company, to assess the project's progress and discuss cooperation strategies. Executives from Doosan Enerbility and Korea Electric Power Technology also accompanied him on part of the visit.


On November 25, Vice President Choi met with executives from the ordering company, EDU II, at the Dukovany site to review follow-up plans for the construction sector and the status of design and permitting preparations. He also attended the opening ceremony of the new Dukovany construction office, which will house about 20 staff members responsible for design and permitting support, collaboration with the ordering company, and site preparations for the start of construction.


Earlier, on November 20, Korea Hydro & Nuclear Power officially concluded its joint cooperation agreement with the Daewoo-Doosan construction consortium for the Dukovany nuclear project and initiated follow-up measures to secure continuity in operations and select a new construction company. The Ministry of Trade, Industry and Energy held the second Team Korea meeting on the Dukovany nuclear project on the previous day, chaired by Minister Kim Jeong-kwan, to review the implementation status of individual companies' project plans.


On November 26, Vice President Choi met with the head of the new business division at Czech Energy Company (CEZ) to discuss plans for the timely submission of the construction permit application in April next year and the commencement of construction in 2029. He was also scheduled to meet with Tomáš Ehler, the head of the nuclear department at the Czech Ministry of Industry, to discuss cooperation strategies for the stable advancement of the nuclear project and the expansion of participation by Czech companies.


Cooperation with local companies will also be strengthened. Vice President Choi met separately with executives from Doosan Skoda Power and Skoda JS to discuss plans for the supply of nuclear equipment and the expansion of project participation.


Next month, Karel Havlíček, the Czech Deputy Prime Minister and Minister of Industry and Trade, will visit Korea. The two countries will hold the fourth Dukovany implementation review committee meeting on December 10 to share specific project plans and discuss ways to expand cooperation in the nuclear supply chain.


Vice President Choi Il-kyung stated, "The Dukovany nuclear project is an important initiative that Korea Hydro & Nuclear Power and Team Korea are advancing based on their accumulated experience and technology in nuclear construction. We will consolidate Team Korea's capabilities to manage key project schedules without disruption and work closely with the Czech government and the ordering company to successfully complete the project."





* This article has been translated by AI.