The battery maker will supply 751 megawatts, or 62.9 percent, of the 1,194 MW awarded, covering nine of 14 sites, including two on Jeju Island. SK On clinched the remaining 443 MW across five inland sites, among them Haenam and Soseong.
Final volumes will be locked in Dec. 4, and operators must finish construction by February 2029.
The third round, tendered at 1,180 MW or about 7.08 gigawatt-hours of storage, exceeded the 1,128 MW awarded in the first two rounds combined. About 85 percent of the new capacity will be built in the North and South Jeolla provinces.
LG Energy Solution, the largest Korean battery maker by production capacity, sat out the round. The company said in a Nov. 5 statement that the decision was based on "selection and concentration" rather than securing short-term volume through price competition.
The result returns Samsung SDI to the top spot in a single round after SK On, shut out of the inaugural round, seized 50.3 percent of the 565 MW awarded in February. Samsung SDI had swept 75.8 percent of the first 563 MW in July 2025.
Samsung SDI now holds about 59 percent of the 2,322 MW allocated over three rounds, followed by SK On at 31 percent and LG Energy Solution at 9 percent. The ministry said it kept a heavy weighting on fire safety and industrial competitiveness, criteria that gained weight from the second round.