Power System Evaluation Standards for Data Centers in the Seoul Area Raised

The passing standard for power system impact assessments for data centers in the Seoul area will increase from 70 points to 75 points. This change aims to alleviate the concentration of high electricity demand in the Seoul area and encourage the distribution of facilities to regions outside the capital that have sufficient power supply.

The Ministry of Climate, Energy and Environment announced on the 15th that it will implement regulations regarding the operation of the power system impact assessment starting on the 16th.

Previously, large power-demand facilities, such as data centers, had concentrated in areas with insufficient power grids, leading to increased overload on the power system and burdens on transmission line expansions. The government has developed this system to guide the decentralization of large power demands after a pilot operation.

During the pilot phase, the status of data center locations showed 28 cases in the Seoul area (1.9 GW) and 64 cases outside the capital (7 GW).

The power system impact assessment is based on the Special Act on the Activation of Distributed Energy and is a procedure to evaluate the effects of large power-consuming facilities on the power system in advance.

This announcement maintains the existing evaluation criteria from the pilot operation while introducing a new criterion for power utilization density. A deduction of 5 points will apply to this new criterion, and the passing standard for data centers in the Seoul area, which have a significant impact on the power system, has been raised from 70 points to 75 points.

The Ministry plans to establish a detailed manual by the end of this year that specifies rapid processing measures and evaluation criteria for each item.

By early next year, a comprehensive information support system will be established to allow operators to manage all related procedures, from document submission to progress tracking and notification of review results, in one place.

Measures have also been put in place to prevent fraudulent applications. The transfer of notification letters regarding power system impact assessment results will be prohibited, and the validity period will generally be limited to one year, with one extension allowed within that timeframe.

Even if an evaluation report was submitted before the announcement took effect, the new standards will apply to operators who have not received notification of review results.

Detailed information on the number of evaluations and capacities by region and industry can be found on the Korea Electric Power Corporation's website.

Lee Jae-sik, Director of Power Network Policy at the Ministry of Climate, stated, "This announcement will strengthen the evaluation of power system impacts and expand preferences for projects located in areas with abundant electricity, contributing significantly to balanced national development and the stable operation of the power system. We will operate a professional review system and procedures for power system impact assessments quickly and transparently to ensure that related systems are effectively implemented in the field."