Samsung and SK Hynix to Occupy Semiconductor Cluster in Gwangju


Gwangju's military airport site will host a semiconductor cluster, with Samsung Electronics utilizing the southern portion and SK Hynix the northern section.

This agreement on land allocation between the two companies comes four months after the site was designated as a candidate for a national industrial complex last July.

The two companies are expected to sign a land lease agreement by the end of this year.

According to the government and Gwangju city on the 19th, after discussions, it was decided that Samsung Electronics will use 1.2 million pyeong of the 2.5 million pyeong area around the Gwangju military airport, while SK Hynix will occupy 1 million pyeong.

The remaining 300,000 pyeong will be used for internal roads and shared infrastructure.

Both companies plan to construct a total of four semiconductor production facilities (fabs), with each building two.

The delay in land allocation was reportedly due to both companies preferring the northern section.

The northern area is closer to the Gwangju Songjeong Station of the Honam High-Speed Railway and the city center, and it has been evaluated as having relatively favorable ground conditions for factory construction and logistics operations.

The government is said to have proceeded with discussions to allocate advantageous locations to companies that can quickly promote factory construction.

Furthermore, it has been decided to prioritize the development of 630,000 pyeong of the total 2.5 million pyeong, including the planned relocation site for ammunition depots, which has minimal impact on military operations.

If all goes according to plan, site preparation work could begin in the first half of next year, with the first phase of the factory expected to be completed by 2029 and the first semiconductor production slated for June 2030.

A key factor is the relocation of the military airport. The Ministry of National Defense plans to temporarily relocate the functions of the 1st Fighter Wing of the Gwangju Air Force Base to Yecheon, Seosan, and Jungwon by mid-2028 to secure the semiconductor industrial complex site.

The National Assembly's Defense Committee also approved a revised budget plan on the 16th to advance the project cost of 103.12 billion won (KRW) for the temporary deployment of the Gwangju military airport to next year's budget.